Battery park Meeden

in Veendam

Panels

Households

Hectares

MW

Gemeente Veendam

Project phase

Last update: 05-03-2025

We have obtained two irrevocable permits for this 500MW battery project. Two permits were required because, due to regulations, we had to divide the project into two parts. In recent months, we have successfully investigated the cable route, which now brings us to the next phase. In this phase, we will conduct additional studies, initiate the procurement process for long-lead-time components, and further refine the details of the cable route. Additionally, we are exploring opportunities to contribute locally to a district heating network and emergency power supply.