Battery park Musselkanaal

in Ter Apelkanaal

Panels

Households

Hectares

MW

Ter Apelkanaal

Project phase

Last update: 11-09-2024

The necessary permit became irrevocable last week. Previously, we had already contracted land and secured a guaranteed 380kV grid connection at the new substation to be built by TenneT. We are eager to begin the implementation and expect this battery to be connected to the electricity grid in 2027. In the coming months, we will conduct additional studies, initiate the procurement process for all components, and further detail the cable route. Additionally, we are exploring local opportunities to participate in an energy hub and establish an emergency power supply.

  • Design
  • Permit
  • Preparation
  • Building
  • In use

Photos

Updates

Leave your details and stay informed of all developments regarding Battery park Musselkanaal - Ter Apelkanaal.

Find out more about this project? Thomas van den Brand is happy to tell you more.